PROJECTS DETAILS

•Project Name: FSF-4 Description: Procurement, construction & commissioning for:

•  42 oil wellheads Piping and mechanical installation .

•  6 OGMs.

•  4 water injection wellheads.

•  Electrical work.

Client Contract Value :

GNPOC  22,000,000 USD.

Duration :

Three Years .

Status : Completed.

Contractor : Ram – PSC consortium.

Project Name: FIELD IMPROVEMENT PROJECT Phase – 1 Description:

•  Smoke Detection System at UPP

•  Potable Water System Modification for all FPFs.

•  New Vent System at Unity FPF

Client Contract Value : GNPOC4,300,000 USD.

Duration : One year.

Status :Completed.

Contractor : RAM ENERGY / PSC.

Project Name: FIELD IMPROVEMENT PROJECT PHASE – II

•Description:

Design, engineering, procurement, construction, installation, testing, pre-commissioning, commissioning, performance test and warranty maintenance of the New Start Air and Instrument Air Packages for Heglig Power Plant facilities.

Client Contract value :GNPOC2,850,000 USD.

Duration : One year .

Status : completed .

Contractor : RAM ENERGY / TECH-SHARP

Project Name: FIELD IMPROVEMENT PROJECT PHASE – III Description:

•An improvement of existing facilities at Alnar, Altoor, Toma South, and Unity FPFs and Heglig CPF.Four buffer tanks (Unity tank:100,000 BL ,Toma South: 50,000 BL , Alnar and Altoor tanks :25,000 BL each).Eight Export Pumps & Additional Isolation Valves, piping at all FPFs with all associated facilities (Electrical, Instrumentation and Control systems) .

•Client : GNPOC

•Contract Value : 15,000,000 USD

•Duration : 11 Months

•Status : completed

•Contractor RAM TECH-SHARP

Project Name: LPG TANKS Description:

•  EPC contract to design & erect LPG Depot with 21,000 capacity at Al-Gaili.

•  consist of 7 LPG Tanks. Erection of the Solar Units.

•  Strategic storage of LPG for Sudan Market.

Client : SPC .

Duration : One Year.

Status : Completed.

Contractor :  CPPE – RAM Consortium.

Project Name: ALGAILI WATER PLANT

Description:

•Treatment plant (50.000m3 /day complete with 7 km, 700 mm transmission pipe line. The main components of the plant are as follows:-Raw Water Intake, Pre chlorination, Roughening tanks (Resettling), Clariflocculators, Sludge treatment, Filtration, Filtered Water reservoirFilters washing system, Low lift pumps, Post chlorination, Treated Water (clean water) reservoir, High lift pump station, Balancing tank (High level tank).

Client : SPC

One Year

Completed

CPPE – RAM Consortium


KSWC

Description:
Treatment plant (50.000m3 /day complete with 7 km, 700 mm transmission pipe line. The main components of the plant are as follows:-Raw Water Intake, Pre chlorination, Roughening tanks (Resettling), Clariflocculators, Sludge treatment, Filtration, Filtered Water reservoirFilters washing system, Low lift pumps, Post chlorination, Treated Water (clean water) reservoir, High lift pump station, Balancing tank (High level tank).
Client : KSWC .
Contact Value 13,300,000 USD .
DURATION 18 months
Status completed .

GREATER NEEM EXPORT PIPELINE

•Description: To transfer the crude from neem FPF to Diffra FPF through a 16″, 100 km long crude oil export pipeline and to provide all equipment and facilities in the neem export pipelines, which will operate at the required capacity and availability as envisaged in the project scope .

•CILENT :GNPOC

•VALUE:12,500,000 USD

•DURATION:1 Year

•Completed

•RAM – PETROJET consortium

UNITY BIOREMEDIATION

•Description:  Bioremediation project is constructed at the CPF & FPF for water Produced from oil to be treatment  with system capacity for the 200,000 barrels/day. The project consists of EPCC storage lagoons, reed beds, gates valves, road crossings and an earth drainage canal, at Unity FPF.

•CLIENT : GNPOC

•DURATION : 1 Year

•STATUS : Completed

•CONTRACTOR :  RAM ENERGY

MANGA BIOREMEDIATION

•Description:

•EPCC Project consist of Pumping Facilities and Dual 20” above ground pipe line for 1 km supported on pile rack.

•CLIENT : GNPOC

•CONTRACT VALUE :  3,500,000 USD

•DURATION : 1 Year

•STATUS : completed

•CONTRACTOR : RAM ENERGY

COMPACT SUBSTATION

•Description: Supply and installation  of Compact Substation at MALA development projects.

•WNPOC RAM ENERGY –

• WEWALTER

• 8 Months

•Finished

TOMASOUTH NEW SWITCHGEARDescription: EPCC of New 33 KV switchgear at TOMASOUTH.

•  Client : GNPOC

•  Value : 2,750,000 USD

•  Status: Completed

THARJATH BIOREMEDIATION WNPOC

•WNPOC

Contract  VALUE : 10,000,000 USD .

Duration ONE YEAR

status COMPLETED

Contractor RAM ENERGY

EARTH MOVING PROJECTS
•Client :PDOC / GNPOC /WNPOC

• Duration :  2 year

• status ONGOING

•Contractor RAM ENERGY

SHENDI – EL MATAMA BRIDGE
•CLIENT :Damps Implementation Unit

•VALUE : 29,200,000 USD

•DURATION : Two year

•STATUS : Completed

•CONTRACTOR :

Ram Energy – Arab Contractors Consortium

OVER HEAD TRANSMISSION LINE PROJECT

•ClientValue1,100,000 USD

• Duration one year

•status Warranty stage

•Contractor Ram Energy

Environment, Health and Safety Policy

•All Companymembers are responsible individually for protecting the environment, health and safety of customers, contractors and community.

•ManagementconsiderhighstandardsforEHSasfundamentalstoourbusinessandcontinuousimprovement.

•Wearecommittedto:

•EHSmanagementsystemwillhelpustopreventmajorincidents,

•greatlyminimizeminorincidents,reduceoperatingcostsandmaintain

•ourcompanyreputationcommittedtocommunityprotection.

•Reducingemissionsandwastes,bestutilizationofenergyand

resources.

•Recordnon-conformities,incidentstoidentifyandsolveproblemsand

•toimplementbestworkpracticesandlessonsshared.

•Promoteoutreachprogramsforthecommunity,customersandpublic

•tokeeptheminformedofoursafeope

Quality Policy

•Ram Energy is a project-oriented company working in the field of Energy and related industries. As a subsidiary of Hi-Tech Group, Ram Energy Co. has been established in 2003 to contribute in enhancing and upgrading the infrastructure of Sudan through providing high quality Engineering services.

•RAM Energy is committed to implement and continually improve a quality Management System (QMS) that covers all company’s activities and complies with the International standards, namely ISO 9001/2000, depending on which; the company ensures maintaining customer satisfaction, confidence and trust.

•The Quality of services aimed at Ram Energy Co. must be fulfilled through the following set of objectives:

•Meet requirements on environment and safety as applicable to our services

•Continually improving the staff performance by implementing the

•necessary training needs.

•Enhancing continuous success in pursuit of improvement of quality of

•services in a cost effective manner.

•Top management ensures that this quality policy shall be distributed, understood and implemented within the company, and shall be reviewed at regular intervals for its continuing suitability.